A) For Development of 4500 MW (4.5 GW) Renewable source i.e. Solar & Wind Energy Park in Rajasthan for HMEL (HPCL – Mittal Energy Limited) work order executed for following scope of work (Already completed)
B) CVK Solar Team under leadership of MD have expertise in development of 1GW to 10GW Solar Park and can provide complete guidance, support and consultancy for stage by Stage development of 1 GW to 10 GW solar Park in Rajasthan in respect of following.
C) CVK Solar Team under leadership of MD have expertise in Design & Planning of economical Power Evacuation System of 400kV, 220kV and 132kV Transmission System having GSS and Transmission Lines for 1GW to 10GW Solar Park and can provide complete guidance, support and consultancy for stage by Stage development of 1 GW to 10 GW solar Park in Rajasthan in respect of following
1) Power Evacuation Planning for 1 to 10 GW Solar Park
· Planning of 100 MW, 200 MW, 300 MW sizes of Plots in Renewable Energy Park
· Line Lengths & Selection of Voltage of transmission lines & their interconnections to GSS
· Locations of 132kV, 220 kV, 400 kV GSS (if required)
· Numbers of 132kV33kV, 220/132/33kV &400/220/132kV GSS
· Switching Scheme of 400kV, 220 kV and 132 kV Yards
· Single line diagram of 400kV, 220 kV and 132 kV GSS
· 220 kV bays in 220kV Yard,132 kV bays in 132 kV Yard, 33 kV Bays in 33 kV Yard
· 400kV Bays in 400 kV Yard
· Lightning Protection Scheme Design
· Overall Substation Lay out planning of 220 kV, 400 kV and 132 kV GSS with various voltage levels in each GSS
· Layout plan of 220 GSS
· Section Diagrams of 220 kV, 132kV bays of 220 kV GSS
· Control, Relay and Protection Scheme of 220kV, 132kV System in 220 kV GSS
· Substation Bus bar design viz Main Bus bar, Bay bus bar design in 220kV yard, 132kV yard in 220 kV GSS
· Control Room Planning and layout
2) Substations Design & Planning
Selection of Switching scheme
· Ring Bus/ Single Bus/ Main Bus/Transfer Bus/ Double Bus/Double Main Bus and transfer Bus / one & half breaker
Selection of System Parameters for transmission evacuation system
· Voltage level 11kV, 33kV, 220kV, 132kV, 400kV
· BIL, SIL, Fault level
· Short circuit & Normal current rating, bus bar ratings
Design based on Short circuit current capacity & selection of Conductor, tube etc for
· Main Bus Bar, Equipment Bus Bar, Transfer Bus Coupler Bay, Transformer Bay, Main Bus coupler bay, Reactor bay, Power Capacitor bank Bay
Design after consideration of Phase to Phase, Phase to earth safety clearance
· Height and spacing in R, Y, B phases of Main overhead bus bar Main, Tubular Bus bar, Overhead bus bar for equipment connection, Over head Connections. Equipment Bay: Equipment to equipment spacing in R, Y, B phases, Equipment Bay: Spacing between two equipment in same phase and interconnections between bus bars & Equipments
Location of equipments based on space optimization and protection scheme
· Circuit Breaker, Isolators, CT, PT, LA, Transformers, wave trap, Main Bus Bars, Transfer Bus Bar
Design of Protection Scheme
· To takecare faults in Transmission lines, Main Bus I Protection Scheme, Main Bus II Protection Scheme, Back up Protection Scheme, Transformer Protection Scheme, Reactor Protection Scheme, Bus bar Protection Scheme, Ground mat design, Lightning Protection Scheme, Lightning mast & Earth wire, shielding from Lightning
D) CVK Solar Team Leader expertise in Design & Planning of economical Power Evacuation System of 400kV, 220kV and 132kV Transmission System having GSS and Lines for 1GW to 10GW Solar Park.
M M Vijayvergia & Others (RRECL, BCB)
203-204, Okay Plus Tower, Near Vishal Mega Mart, Opp. Government Hostel, Jaipur-302001 (Rajasthan) INDIA.
(+91) 141 2365505 / +91-9982044488 / +91-9950611113,15 / 7340024336,38
info@cvksolar.in